The 8500-tonne launch jacket for DONG's Hejre field offshore Denmark has sailed from Heerema Fabrication Group's Heerema Vlissingen facility in the Netherlands (pictured). HFG's contract, which was with Technip, covered the procurement and construction of a jacket…
A year of significant construction work on the Cygnus gas project by Burntisland Fabrication (BiFab) came to fruition recently as major infrastructure sailed out from the yard in Methil, Fife. Operator GDF SUEZ E&P UK Ltd (38.75%) and partners Centrica Energy (48…
Heerema Fabrication Group (HFG)'s Vlissingen facility has completed the HelWin bèta jacket for client Siemens and the structure has set sail to its offshore location in the German sector of the North Sea. After the EPC (engineering,procurement…
Heerema Fabrication Group’s (HFG) Vlissingen yard in the Netherlands celebrated the first steel cut on the Gina Krog jacket, the largest launch jacket built at HFG. The 17,000-ton jacket is being built for Statoil Petroleum AS and is…
Dockwise provides this video, filmed in November 2012, regarding the launch of the SHP jacket, now located at the SHWE field in the Bay of Begal, off Myanmar. The 22,000-ton jacket was launched at a water depth of 110m, using the HYSY229 installation barge.
Heerema Fabrication Group’s Vlissingen fabrication yard has completed the fabrication of two jackets for the Golden Eagle Development project of Nexen Petroleum UK Ltd. With the departure of Nexen’s 6,400-ton PUQ (Production Utilities…
Using multiple work centers and close project management, L&T delivered the MNP jacket on schedule. Larsen & Toubro (L&T), India was awarded the Mumbai High North (MHN) process platform, living quarters, and process gas compressor module project by ONGC…
Heerema Fabrication Group (HFG) in the Netherlands has received the contract from Technip France for the Procurement and Fabrication of the DONG Hejre jacket, piles and pre-drilling wellhead deck destined for the Hejre oil & gas field located in the central part of the North Sea offshore Denmark…
Statoil contracted Heerema Fabrication Group’s Vlissingen yard for the engineering, procurement, and construction of a fixed jacket and pre-drilling module for the Dagny field development in the central North Sea. The 16,000-ton jacket will be the largest launch jacket built at the yard.
Rotterdam-based transporter Fairmount Marine delivered Noble’s Tamar jacket to the eastern Mediterranean last month. The 18,500ton jacket was built in Corpus Christi, Texas, and traveled 9000 miles from the US on Heerema Marine Contractor’s H851 barge towed by Fairmount Marine’s tugs…
The North Sea-bound jacket weighs 16,000 tonsDagny Jacket (Image: Heerema Fabrication Group)Heerema Vlissingen to set another record breaking fabrication project of the largest launch jacket ever built at HFG Heerema Fabrication…
Iranian Offshore Engineering & Construction announced that its 3300t jacket is bound for South Pars field. The 67m high jacket will be installed 115km off Asalouyeh, Iran, in 61m of water.
An impressive example of lean design and fast-track construction of a major offshore structure is now standing in 133m of water in the Norwegian North Sea. Adrian Cottrill looks at the technology-stretching jacket at the heart of Statoil's NKr20…
All the careful planning and refinement of the Valemon jacket design finally paid off on 18 June when the structure's record-breaking offshore lift-installation was completed. At 03.00 hours, the base of the 160m high steel frame finally touched the seabed…
Decommissioning and abandonment specialist Cutting Underwater Technologies (Cut) assisted Heerema's Thialf with the removal of the Norpipe 37/4A booster platform's eightlegged steel jacket as part of Norway's Ekofisk cessation project. The 5500t platform stood in 85m of water…
AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week